Due to the impact of Covid-19, the overall development of windfarm has been delayed for nearly 2 month, by June 13th the first batch of pin piles has arrived in TPC windfarm and ready to be piled.
TPC windfarm is located at 7.2km to 8.7km out side of Changhua, designed with 21 turbine with 5.2MW each, total capacity 109.2MW.
The transportation scope is carried by the new purchased AHT (Orient No.8) and Barge (DF Buffalo) by Hunghua Construction and operated by Dong Fang Offshore. It is the first foundation transportation been carried out by Taiwanese company to windfarm, the success of this transportation project has demonstrated the capability of Taiwan local marine supplier.